Utviklingshastighet
| Sprint | Est. velocity | Est. fokusfaktor | Fullførte stories | Faktisk fokusfaktor | Unplanned | Kommentar |
|---|---|---|---|---|---|---|
| Sprint 1 | 30 | 60% | 30 | 60% | ||
| Sprint 2 | 23 | 60% | 23 | 60% | ||
| Sprint 3 | 30.5 | 60% | 27.5 | 54% | ||
| Sprint 4 | 29.5 | 60% | 25.5 | 51% | Smidig2014 | |
| Sprint 5 | 30 | 60% | 24 | 48% | Personreg v2 prodsetting | |
| Sprint 6 | 18 | 60% | 14 | 47% | Eksterne avhengigheter | |
| Sprint 7 | 19 | 60% | 12 | 38% | Eksterne avhengigheter | |
| Sprint 2015-1 | 25 | 60% | 17 | 41% | Eksterne avhengigheter | |
| Sprint 2015-2 | 22 | 60% | 21.5 | 58% | Eksterne avhengigheter | |
| Sprint 2015-3 | 29 | 60% | 24.5 | 51% | Eksternt og internt | |
| Sprint 2015-4 | 24.5 | 60% | 20.5 | |||
| Sprint 2015-5 | 23.5 | 60% | 8.5 | |||
| Sprint 2015-6 | 26.4 | 60% | 28 | |||
| Sprint 2015-7 | 21.5 | 60% | 17 | |||
| Sprint 2015-8 | 22 | 60% | 22 | 60% | 1+ | |
| Sprint 2015-9 | 19 | 60% | 0? | 2 veker, sommarferie | ||
| Sprint 2015-10 | 32 | 60% | 31 | |||
| Sprint 2015-11 | 24 | 60% | 24 | 60% | ||
| Sprint 2015-12 | 31 | 60% | 26 | Feature freeze Cerebrum, nytt prodmiljø | ||
| Sprint 2015-13 | 34 | 60% | 19 | 5+ | Prodsetting Delegate | |
| Sprint 2015-14 | 30.5 | 60% | 19.5 | 8+ | Mykje feil rundt broker og ePhorte, samt valgshenvendelser | |
| Sprint 2015-15 | 30.5 | 60% | 6.8 | 1+ | Mykje meir kompliserte oppgaver, sterkt underestimert | |
| Sprint 2015-16 | 15 | 55% | 2 | 2 veker, julefri og ein del sjukdom mot slutten |
Skal plotte inn estimert velocity (utviklingshastighet) og samanlikne det med faktisk velocity. Dette har fleire formål:
- Rekne ut ein passande fokusfaktor for seinare sprintar. Om det er stor skilnad mellom estimert og faktisk velocity betyr det at vi har hindringar, til dømes at deltakarane må bruke masse tid på arbeid utanfor sprinten, eller dårleg estimering.
- Sjå om utviklingshastigheten i gruppa utvikler seg.
Som graf har vi då utviklinga: